What's New

On-Going Project : Laguna Water

Wednesday, June 29, 2016

On-Going Project : Laguna Water

The Biñan Well Field Reservoir and Transmission Line Package 1 Project is composed of the following: erection of  4 – 5MLD steel bolted reservoir, construction of a pumping station that houses 4 – 5MLD Booster pumps, and a  5 km water distribution pipes.

The project aims to increase the water supply and service coverage of Laguna Water on the nearby area.


Contract details:
Start Date: April 28, 2015
End Date: July 20, 2016
Client: Laguna AAA Water Corporation


back